top of page
Veronica Dr, Horizon Dr & Smith Rd
Project Status: Stabilization Period
Project Notes:
Veronica Dr - Tree removal and trimming, reclaimed the entire road (recycle the existing asphalt into the road base), completed fine grading, a full 4” repaving effort (2.5” binder, 1.5” wearing still to be installed this fall), lawn restoration work, and the installation of compacted shoulder gravel. Project completion is anticipated in early fall 2024.
Horizon Dr - Installed drainage ditches near the intersection of Veronica Drive, some tree removal and trimming, installed pavement shim to reestablish road profile, and then perform a 1.5” overlay in the same area, lawn restoration work. Project completion is anticipated in early fall 2024.
Smith Rd - Performed camera inspection of the existing drainage system, and replaced/240 lf of pipe, and installed a direct Inlet structure to address a wet area in the same area, to prevent an icing issue. Tree removal and trimming, remove several damaged areas of pavement and repave (2” spot inlays). Finally, a full pavement overlay, and compacted shoulder gravel will be installed this fall.
bottom of page