top of page

Quincy Drive and Shepherd Hill Rd

Project Status: Substantially Complete

Project Notes: 
Shepherd Hill Rd - Replaced two failed culverts, regrading in the cul-de-sac to promote better drainage, some tree removal and trimming, reclaimed the entire road (recycle the existing asphalt into the road base).  Finally, fine grading, a full 4” repaving effort (2.5” binder complete, 1.5” wearing still to be installed this fall), lawn restoration work, and the installation of compacted shoulder gravel.  Completion of the project is anticipated in late fall 2024.
Quincy Dr - The work that was performed is, some tree removal and trimming, remove several damaged areas of pavement and repave with 2” spot inlays, and finally install 2’wide compacted shoulder gravel in repaved areas.  This project is complete.

QuincyShepherd.jpg
bottom of page