On Wednesday September 13, 2017, the construction of the new gas main on Donald Street will commence, this project is expected to be completed in 45 working days. Donald Street will be subject to alternating one way traffic in the area during the hours of 7:00 am to 5:00 pm during the entire project. Expect delays and seek alternate routes. Operational signs and flaggers will be in place to assist motorists.
Work Schedule
Wednesday Sept. 13th -Tuesday Sept. 19th
Donald St. from Swan Av. To 100’ west of Old Bedford Rd.
Wednesday Sept. 20th -Tuesday Sept. 26th
Savoie St. Donald St. to End
Wednesday Sept. 27th -Tuesday Oct. 3rd
Swan St. from Donald St. to End
Darling St. Swan St. to End
Tuesday Oct. 3rd -Friday Oct. 13th
Woodlawn Av, Lawes Av, and Services to homes along route.
Monday Oct. 15th - Finish
Complete miscellaneous services to homes along route and cleanup.